File #: 15-322    Version: 1 Name:
Type: Staff Report Status: Passed
File created: 6/1/2015 In control: City Council
On agenda: 6/17/2015 Final action: 6/17/2015
Title: AWARD CONTRACT FOR 2015 PAVEMENT RESURFACING PROJECT
Attachments: 1. 2015 Pavement Resurfacing Project location Map, 2. Resolution for Award of 2015 Pavement Resurfacing Project, 3. Contract for 2015 Pavment Resurfacing Project
CITY COUNCIL STAFF REPORT
MEETING DATE: JUNE 17, 2015

PREPARED BY: Scott Creer, Senior Engineer/Public Works Engineering
APPROVED BY: City Manager

TITLE
AWARD CONTRACT FOR 2015 PAVEMENT RESURFACING PROJECT
END

RECOMMENDATION(S)
RECOMMENDATION
Adopt Resolution approving the following actions:
1. Approve project plans and specifications;
2. Award a contract to C.F. Archibald Paving, Inc. for the 2015 Pavement Resurfacing Project in the amount of $995,810;
3. Authorize expenditure of construction contingency funds not to exceed $99,581; and
4. Authorize the City Manager to execute and administer the construction contract with C.F. Archibald Paving, Inc.

BODY
COUNCIL PRIORITIES, GOALS & STRATEGIES:



Ongoing Priorities
Enhancing public safety




REPORT NARRATIVE:
The scope of work for this project includes Asphalt Concrete (AC) overlay, full depth AC pavement repair, and crack seal work. The streets to be overlaid with this project are East Dunne Avenue from Condit Road to Hill Road and Tennant Avenue from UPRR right-of-way to Vineyard Boulevard. The treatment types and locations were selected based on information obtained from the City's Pavement Management Program and through visual inspection by city staff.

In soliciting bids, the City advertised in the Morgan Hill Times newspaper and sent bid packages to eleven Builders Exchanges, ranging north/south between San Francisco and Salinas and east/west between Acampo and Santa Cruz.

The bid opening was held on June 4, 2015 and the bids received are listed below. The low bidder has years of experience doing this type of work and has performed similar work in the City during the last 4 years. Staff recommends award of the contract to C.F. Archibald Paving, Inc. The project is scheduled to begin in August 2015 and be completed by September 2015. C.F. Archibald Paving, Inc. bid was 16% lower than the engineer's estimate of $1,159,767.

C.F. Archibal...

Click here for full text