File #: 15-846    Version: 1 Name:
Type: Staff Report Status: Consent Calendar
File created: 12/1/2015 In control: City Council
On agenda: 12/16/2015 Final action: 4/1/2016
Title: APPROVE RIGHT OF WAY AND SLOPE EASEMENT DEDICATIONS TO THE COUNTY OF SANTA CLARA FOR THE DEWITT AVENUE S-CURVE REALIGNMENT PROJECT
Attachments: 1. Resolution-Dewitt S-curve Dedication, 2. Exhibit A to Resolution, 3. Project Location Map

CITY COUNCIL STAFF REPORT                       

MEETING DATE: December 16, 2015

 

PREPARED BY:                     David Gittleson, Associate Engineer, Public Works-Engineering                                           

APPROVED BY:                     City Manager                                          

 

Title

APPROVE RIGHT OF WAY AND SLOPE EASEMENT DEDICATIONS TO THE COUNTY OF SANTA CLARA FOR THE DEWITT AVENUE S-CURVE REALIGNMENT PROJECT

END

 

RECOMMENDATION(S)

RECOMMENDATION

Adopt resolution approving the following actions:

1.                     Approve right of way and slope easement dedications to the County of Santa Clara for the DeWitt Avenue S-Curve Realignment Project, and

2.                     Authorize the City Manager to sign the right of way and slope easement grant deeds, and

3.                     Direct the City Clerk to record the right of way and slope easement deeds with the County of Santa Clara.

 

BODY

COUNCIL PRIORITIES, GOALS & STRATEGIES: 

 

Ongoing Priorities

Enhancing public safety

Maintaining fiscal responsibility

 

 

2015 Focus Areas

Participate in Regional Issues

Infrastructure Funding and Advocacy

Advance Regional Transportation

REPORT NARRATIVE:

The County of Santa Clara is proposing to complete the DeWitt Avenue "S" Curve Realignment project between Spring Avenue and Edmundson Avenue. The realignment will substantially improve the safety of the roadway at that location.  The County of Santa Clara is the lead agency for the project because that portion of DeWitt lies within their jurisdiction.  The City has agreed to help pay for the project and has allocated funds in the approved FY 15/16 Capital Improvement Program (CIP) budget. 

 

The design of the project is roughly 95% complete and the realignment requires right of way purchases from the adjacent land owners.  The City of Morgan Hill is one such land owner as the City owns APN 767-15-024 (Edmundson Reservior property).  Thus, the County needs 2,131.95 SF of right of way and 4,014.29 SF of slope easement from the City to construct the improvements.  Attached are the legal descriptions and plats of the land needed for the project. 

 

Staff has evaluated the area requested for the taking and finds the impacts to the City-owned property to be minimal.  In addition, the value of this land is considered minimal and that the costs of documenting the sale would come close to the value of land, therefore, granting the land to the County of Santa Clara is a reasonable contribution by the City.  Given that and the City's role as a stakeholder in the project, staff recommends granting the right of way and easement to the County for no charge. 

The latest schedule from the County shows them completing the right of way acquisitions in May 2016 and commencing with construction in July 2016.  Construction is estimated to take 150 working days which would place the completion roughly in December 2016.  

 

COMMUNITY ENGAGEMENT:                     Inform

The project is not estimated to begin construction until July 2016 at the earliest. Staff will work closely with County officials to ensure they notify affected property owners and the community prior to construction activities.  Notifications may include, email, website, mail, and/or newspaper. Residential driveway and emergency vehicle access will be provided. Those residents who own property required by the project have already been notified by the County of Santa Clara.   

 

ALTERNATIVE ACTIONS:

o                     City Council could elect to not dedicate the necessary easements for the road improvements; however, this would force the County of Santa Clara to re-engineer the project thereby increasing cost and delaying the safety improvements.

o                     City Council could choose to sell the required land in fee title; however, this method of property transfer would cost more and take longer to process.

 

PRIOR CITY COUNCIL AND COMMISSION ACTIONS:

o                     City Council first approved this project in June 2012, when the FY 12/13 Capital Improvement Program was adopted.  City Council also approved the project in the following FY 13/14 and FY 14/15 Capital Improvement Program years.

o                     On June 17, 2015, City Council adopted the FY 15/16 Capital Improvement Program, which also included the DeWitt Avenue S curve Realignment Project.

 

FISCAL AND RESOURCE IMPACT:

No impact to the fiscal budget. The City’s portion of the project is budgeted in the FY 15/16 CIP Program under #562012-DeWitt Avenue "S" Curve Realignment with a total budget of $1,003,000.  Of that, $520,000 is funded from Traffic Impact Fund (309), $350,000 from Water System Replacement Fund (653) bonds, and $133,000 from the Water System Replacement Fund (653).

 

CEQA (California Environmental Quality Act): 

Not a Project

 

LINKS/ATTACHMENTS:

Resolution

Exhibit A to Resolution

Project Location Map