File #: 16-452    Version: 1 Name:
Type: Staff Report Status: Consent Calendar
File created: 6/10/2016 In control: City Council
On agenda: 9/7/2016 Final action:
Title: ACCEPTANCE OF DOWNTOWN UNDERGROUNDING UTILITIES STREET IMPROVEMENT PROJECT (SIDESTREET RENOVATION)
Attachments: 1. Resolution for Completion for Downtown Undergrounding utilities Street Improvement Project, 2. Notice of Completion for Downtown Undergrounding Utilities Street Improvement Project (1), 3. Accept Downtown Undergrounding Utilities Street Improvement Project Change Order Closeout, 4. Project Location Map Downtown Undergrounding Utilities Street Improvement Project

CITY COUNCIL STAFF REPORT                       

MEETING DATE: September 7, 2016

 

PREPARED BY:                     Karl Bjarke, Public Works Director                                            

APPROVED BY:                     City Manager                                          

 

Title

ACCEPTANCE OF DOWNTOWN UNDERGROUNDING UTILITIES STREET  IMPROVEMENT PROJECT (SIDESTREET RENOVATION)

END

 

RECOMMENDATION(S)

RECOMMENDATION

Adopt resolution approving the following actions:

1.                     Accepting as complete the Downtown Undergrounding Utilities Street Improvement Project in the final amount of $2,221,314;

2.                     Authorizing the Public Works Director to sign the attached Notice of Completion; and

3.                     Directing the City Clerk to file said Notice of Completion with the County Recorder's Office.

 

BODY

COUNCIL PRIORITIES, GOALS & STRATEGIES: 

 

Ongoing Priorities

Enhancing public safety

Maintaining fiscal responsibility

 

 

2016 Focus Areas

Planning Our Community

Developing Our Community

 

REPORT NARRATIVE:

On June 17, 2015, City Council awarded the contract for the Downtown Undergrounding Utilities Street Improvement project to St. Francis Electric, LLC. in the amount of $1,871,464.  In addition, City Council approved contingency funds not to exceed an amount of $280,720.  Subsequent to the start of the project, at its September 2, 2015 meeting, City Council approved an appropriation of $150,000 in order to complete the necessary slurry seal and striping in the Downtown.  In all, the total authorized project amount is $2,302,184.       

 

The scope of work for the project includes the undergrounding of overhead utilities and new street lights on First Street, Second Street, and Fourth Street, between Monterey Road and Depot Street.  The purpose of the project is to visually enhance these street corridors by removing unsightly overhead wires and utility poles and to improve safety for the public and first responders.  In addition, the scope included the installation of a new water line and sewer line in Fourth Street and striping and slurry seal in the Downtown.

 

Nine contract change orders were issued during the project totaling $349,850. Thus the total construction contract amount is $2,221,314 (base contract amount of $1,871,464 + total change order amount of $349,850).  This is less than the authorized amount of $2,302,184 and, thus, the project balance of $80,870 will be returned to the RDA Bond Proceeds Fund (250). The work has been completed per the contract documents and, thus, staff recommends accepting the project. 

 

 

 

COMMUNITY ENGAGEMENT:                     Inform

 

At the March 4, 2015 City Council Meeting, Council held a Public Hearing for the formation of an Underground Utility District.  Staff and the contractor regularly communicated with affected property owners during construction.

 

ALTERNATIVE ACTIONS:

Accepting the improvements once the contract is complete in accordance with the contract documents is a required process to complete the construction contract and enables the City to release any retained funds owed to the contractor per the California Public Contract Code Section 7107.

 

PRIOR CITY COUNCIL AND COMMISSION ACTIONS:

o                     May 21, 2014 - At City Council Meeting, staff presented and the Council approved the Downtown Placemaking Investment Strategy for expenditure of 2008 Bond proceeds that includes streetscape improvements, pedestrian safety improvements, landscape/irrigation to the median along Monterey Road, parking lot improvements, and undergrounding of the overhead utilities.

 

o                     February 4, 2015 - At the City Council Meeting, Council directed staff to notice the required public hearing to be held on March 4, 2015 for the formation of an Underground Utility District along First Street, Second Street, and Fourth Street between Monterey Road and Depot Street per Morgan Hill Municipal Code, Chapter 12.12.

 

o                     March 4, 2015 - At the City Council Meeting, Council adopted the resolution establishing Downtown Underground Utility District (DUUD) on First Street, Second Street, and Fourth Street between Monterey Road and Depot Street.

 

o                     June 4, 2015 - At the City Council Meeting, Council adopted the resolution approving and authorizing the City Manager to execute a Service Agreement for Design Professionals with Sandis for a not-to-exceed fee of $335,510 for several design tasks related to the Downtown Placemaking Investment Strategy, including undergrounding overhead utilities in the Downtown.

 

o                     June 17, 2015 - At the City Council Meeting, City Council awarded a contract to St. Francis Electric, LLC for $1,871,464 for the Downtown Undergrounding Utilities Street Improvement Project.

 

o                     September 2, 2015 - At the City Council Meeting, City Council re-appropriated $150,000 from 2015-16A ROPS line 99 to line 105, Monterey Road Improvements, for the slurry seal and striping that was estimated to cost $150,000. 

 

FISCAL AND RESOURCE IMPACT:

The approved FY 2014/15 and 2015/16 CIP Budgets include the downtown projects and associated implementation costs. The bond proceeds expenses for these services were included in the approved ROPS 14-15B and the ROPS 15-16A submittal approved by the Oversight Board and by the State Department of Finance.  The total construction authorization for this project is $2,302,184, which includes the original award of the contract, a contingency of $280,720, and a later authorization of $150,000.  The final contract amount is $2,221,314.  The unused balance for this project will be $80,870 and shall be returned to Fund 250 (and expended on other downtown placemaking projects).

 

CEQA (California Environmental Quality Act): 

Categorical Exemption

 

Per Section 15301 of the CEQA Guidelines setting forth a categorical exemption for existing facilities.

 