File #: 17-109    Version: 1 Name:
Type: Staff Report Status: Other Business
File created: 2/16/2017 In control: City Council
On agenda: 2/22/2017 Final action:
Title: AWARD OF THE DOWNTOWN PARKS PROJECT
Attachments: 1. Attachment 1 February 15 Staff Report, 2. Contract for Suarez and Munoz 2-15-17, 3. Resolution budget amendment, 4. Exhibit A to Resolution - Budget Amendment Fund 301, 5. Exhibit B to Resolution - Budget Amendment Fund 346, 6. Project Location Map Downtown Parks Project, 7. Site Plans, 8. Plans and Specifications, 9. Presentation

CITY COUNCIL STAFF REPORT                       

MEETING DATE: February 22, 2017

 

PREPARED BY:                     Yat Cho - Senior Project Manager/Engineering & Utilities Department
                                                                                    Chris Ghione - Director/Community Services Department

APPROVED BY:                     City Manager                                          

 

Title

AWARD OF THE DOWNTOWN PARKS PROJECT

END

 

RECOMMENDATION(S)

RECOMMENDATION

1.                     Adopt a resolution amending the Fiscal Year 2016/17 Budget and appropriating an additional $1,053,000 from the Park Impact Fund (301) and appropriating $1,000,000 from the Public Facilities Fund (346);

2.                     Approve project plans and specifications;

3.                     Award contract to Suarez and Munoz Construction, Inc. for the Downtown Parks Project in the amount of $5,030,000;

4.                     Authorize the expenditures of construction contingency funds not to exceed $503,000; and

5.                     Authorize the City Manager to execute the contract.

 

BODY

COUNCIL PRIORITIES, GOALS & STRATEGIES: 

 

Ongoing Priorities

Enhancing Public Safety

Supporting Our Community

Protecting the Environment

 

2017 Strategic Priorities

Infrastructure

 

REPORT NARRATIVE:

On February 15, 2017, the City Council tabled the Award of the Downtown Parks Project to the meeting of February 22, 2017. The purpose of this continuance was to evaluate this item after reviewing the priorities outlined in the Bikeways, Trails, Parks and Recreation Master Plan (Plan) to be presented the same evening. The February 15 Staff Report can be found as Attachment 1.

 

The primary concern outlined by the Council was the appropriation of Park Impact Funds (301) for the project that would push back implementation of other projects outlined in the Plan. After considering the Council’s discussion and the availability of funds in the Public Facilities Fund 346, staff recommends the Council appropriate $1.0 million of the additional $2.05 million needed to construct the Downtown Parks from Fund 346 to support road reconstruction, bridge construction, and the restroom facilityPublic Facilities Fund revenues are voluntary contributions received from developers of properties and the funds may be used for the design, construction, and maintenance of public facilities or to reimburse the City for funds advanced to construct such facilities. The appropriation of funds from Fund 346 would reduce the necessary appropriation from Fund 301 to $1.05 million. By using this additional funding source, more funding would be available in Fund 301 for other projects in the Plan, while moving forward with the Downtown Parks Project.

 

 

 

LINKS/ATTACHMENTS:

1)                     February 15, 2017 Staff Report

2)                     Construction Contract

3)                     Resolution

4)                     Exhibit A to Resolution - Budget Scorecard

5)                     Exhibit B to Resolution - Budget Scorecard

6)                     Project Location Map

7)                     Site Plans

8)                     Plans and Specifications (<http://www.morgan-hill.ca.gov/DocumentCenter/Index/1954>)

9)                     Presentation