LIBRARY, CULTURE & ARTS COMMISSION STAFF REPORT                       

MEETING DATE: March 7, 2017

 

PREPARED BY:                     Chris Ghione, Community Services Director                                          

 

Title

DOWNTOWN PARKS RELATED ART PROJECTS

 

RECOMMENDATION

Review Timeline for Downtown Art Projects.

 

BODY

 

REPORT NARRATIVE:

During review of it’s the Commission Work Plan at the July 5th Meeting of the LCAC, a sub committee was formed to look into the opportunity of creating a Bike Rack Art Program.  The sub-committee subsequently met and proposed creating as similar program to what was done by the City of Los Altos, http://www.losaltosca.gov/publicartscommission/page/los-altos-bike-rack-design-competition. On August 2, 2016 the Commission recommended the Bike Rack Art Contest be included in the concept designs for the downtown parks.

 

On February 22, the City Council approved the Downtown Parks Project and included funding for Public Art in the following amounts:

-                     Bike Rack Art Contest - $15,000

-                     Mural on Depot Street Park Sound Wall - $20,000

-                     Sculpture or Other Art for the Downtown Creek park - $15,000

 

With the understanding that several members of the Commission will be changing this coming month, staff is recommending that the Commission wait until the April meeting to coordinate sub-committees to work on the art projects. The following schedule is proposed:

 

February 22, 2017                     Approval by City Council as a component of Downtown Parks Approval

April 3, 2017                                          LCAC Finalize Submission Guidelines

                                                               Develop Sub-committees for each project

April 15, 2017                     Promotion of Contest/Call for artists begins

May 31, 2017                     Submission Deadline Closes

June 30, 2017                     Online Voting Concludes

July TBD, 2017                     LCAC Review

July 19, 2017                                          City Council Review                     

July 31, 2017                                          Contracts for Fabrication or Art are Complete

July-Nov 2017                     Fabrication Completed

November 2017                     Installation/Opening

 

It is recommended that the Commission discuss the timeline and provide any recommendations to staff on things to be included in the submission guidelines.